Equinox Gold Corp. announced that mining activities are under way in the Piaba Deposit at its Aurizona gold mine in Brazil. Construction remains on track to pour gold by late 2018. The mining contractor, U&M Mineração e Construção S/A, mobilized to site in March and mining commenced in mid-April. The majority of the mining fleet is on site and U&M has filled most of the planned 200 operator and support positions. U&M is operating two shifts a day and at the start of June will implement a third shift to mine 24 hours a day, seven days a week. Mining activities are currently focused on removing waste from two locations in the Piaba pit and developing access roads in preparation for ore mining in the third quarter of 2018.