Following completion of a feasibility study into the viability of operating a milling facility at its Kışladağ gold mine in western Turkey, Eldorado Gold has elected to proceed with construction of the project. The mine until now has produced gold via heap leaching; however, the company stopped stacking ore on the leach pad in April. Production since then has been from the remaining inventory on the pad. Production for 2018 is forecast to be in the range of 160,000 ounces (oz) to 170,000 oz of gold.