Coeur Mining reported Q2 production output at 4.6 million oz silver, a 21% improvement over Q1. Silver and gold production at the company’s Palmarejo mine in Mexico, with increases of 24% and 23%, respectively, were strong contributors to the quarter-on-quarter growth.

"Our operations and technical teams deserve tremendous credit for the improvements,” said CEO Mitchell J. Krebs. “We remain enthusiastic about the expansion initiatives.”

The company reaffirmed 2013 full-year production guidance of 18-19.5 million oz of silver and 250,000-265,000 oz of gold. Coeur is also maintaining full-year cash operating cost guidances of $9.50/oz-$10.50/oz for silver, which reflects ongoing cost reduction efforts.

Coeur said it will seek recovery enhancements at Palmarejo to boost silver and gold rates by 5% to 10%. Re-sequencing of higher-grade stopes at Kensington in Alaska is expected to yield a 10% higher grade and increase production by 25%, while decreasing unit operating costs by 20%.

The company plans to complete a $15.1-million improvement program at its San Bartolomé mill by Q4, which is expected to increase silver production by 10% to 15%.

Company officials announced plans to reduce exploration expenses by 17%—or $3 million—through Q4 2013, while reallocating an additional $3 million of reductions to the La Preciosa project. This will be accompanied by the elimination or deferrment of $24 million in capital projects scheduled for 2013.

Resource Center Whitepapers, Videos, Case Studies

Let's stay in touch!

All of the latest mining news and our digital edition sent to your inbox once a week.

We'll never share your email address, and you can opt out at any time, we promise.