Following work suspension amid disputes with government officials, Vale said the cost to develop a project making Argentina the world’s third-largest potash supplier could have doubled to $11 billion from inflation and currency exchange rate fluctuations. Vale has announced it would shelve the project after Buenos Aires officials denied it $3 billion in tax relief under concession rules; Argentina has since announced it would revoke the project licenses if work fails to resume. The presidents of Argentina and Brazil are scheduled to meet by mid-April to resolve the issue.

“We’ve tried to reach some agreement with the government for many and many months,” CEO Murilo Ferreira told reporters at a Hong Kong conference, according to Bloomberg News. Despite the disagreements, however, Ferreira voiced optimism that laws would “prevail.”

Previously budgeted at $5.9 billion, Vale officials announced at the end of February that they completed 45% of the Rio Colorado project for $2.23 billion. The project includes development of a mine in western Argentina, renovating 440 km of railway infrastructure and building a 350 km linking the site to the port of Bahia Blanca.

With a 4.3 million-ton capacity, the project in Mendoza Province would make Argentina the world’s third-largest potash exporter, said President Cristina Fernandez de Kirchner, upon the deal’s initial July approval. Kirchner’s nationalist agenda is deemed a direct threat to resource extraction companies in Latin America’s third-biggest economy; since 2007, her socialist governance has also caused serious contractions—runaway inflation being one of its main causes. 

Resource Center Whitepapers, Videos, Case Studies

Let's stay in touch!

All of the latest mining news and our digital edition sent to your inbox once a week.

We'll never share your email address, and you can opt out at any time, we promise.