Extorre Gold Mines announced in early April 2012 the results of preliminary economic assessment (PEA) No. 3 for its Cerro Moro gold-silver project in Santa Cruz province, southern Argentina. The PEA considered mine production scenarios ranging from 1,000 to 1,500 mt/d. A 1,300-mt/d scenario was selected as the preferred scenario and is the basis for the information reported here.

At the 1,300-mt/d mining rate, Cerro Moro precious metal production over a nine-year mine life is estimated at 848,000 oz of gold and 47.2 million oz of silver, for a total gold equivalent production of 1.79 million oz. Gold contributes approximately 48% of the projected revenue stream, and silver contributes approximately 52%. During the first five years of operations, gold equivalent production would average 248,000 oz/y. The economic modeling used base-case metal price assumptions of $1,320/oz for gold and $26/oz for silver.

The Cerro Moro PEA contemplates a combination of approximately 43% open-pit and 57% underground mining. Mine-site cash costs during the first five years are estimated at $304/oz on a gold equivalent basis. Initial capital expenditures are estimated at $284 million, including refundable VAT.

DFP Boombox Upper

 
 
 

Resource Center Whitepapers, Videos, Case Studies

Let's stay in touch!

All of the latest mining news and our digital edition sent to your inbox once a week.

We'll never share your email address, and you can opt out at any time, we promise.