Guyana Goldfields reported positive feasibility study results in late February 2012 for its 100%-owned Aurora gold project, located about 170 km west of Georgetown, Guyana, South America. The mine plan contains 45.2 million mt of ore grading 3.17 g/mt gold.

Total gold production over a 22-year mine life is estimated to be 4.359 million oz, averaging 256,800 oz/y for the first 10 full years (2015 to 2024). Ore production will begin from an open-pit in 2014 at an average production rate of 8,000 mt/d for the first five years. Production from underground mining will begin in 2019 and will gradually replace open-pit feed.

Capital costs to the beginning of open-pit production are estimated at $525 million. Capital spending from 2014 to 2019 to develop the underground mine is estimated at $465 million. Operating cash costs over the life of the project are projected to average $522/oz. Total operating costs (with royalty) are anticipated to average $626/oz.

The Aurora project has proven and probable reserves of 4.6 million oz of contained gold. The feasibility study was based on 291,556 m of core drilling in 939 holes drilled between 2004 and May 2011. Drilling has been ongoing since May 2011, and Guyana Gold expects to issue a revised resource calculation in late 2012.

The Aurora ore is free-milling, allowing a flowsheet using conventional gold processing techniques. The only metal to be recovered is gold and recovery is excellent at a grind size of 80% passing 75 μ.

Testwork has shown that approximately 30% of the gold can be recovered in the gravity circuit. The remaining gold in the ore will be leached in cyanide followed by carbon-in-leach (CIL) gold recovery.

DFP Boombox Upper

 
 
 

Resource Center Whitepapers, Videos, Case Studies

Let's stay in touch!

All of the latest mining news and our digital edition sent to your inbox once a week.

We'll never share your email address, and you can opt out at any time, we promise.