Dacian Gold has achieved another key development milestone at its Mount Morgans gold project, located 25 kilometers (km) southwest of Laverton in Western Australia, with underground mine development at Beresford intersecting first ore on October 4, four weeks ahead of schedule.

Underground mining commenced at Beresford in mid-May and, by the end of September, 1,837 meters (m) of underground development had been completed compared with the feasibility study schedule of 1,509 m, a total of 328 m ahead of schedule.