Kinross Gold will wait until 2015 at the earliest to make a construction decision on enlarging its Tasiast gold mine in Mauritania. If the project is approved, it will allow Tasiast to eventually reach a production level of 848,000 oz/y in the five years following the tentative expansion. (Photo courtesy of Kinross Gold)
Kinross Gold will wait until 2015 at the earliest to make a construction decision on enlarging its Tasiast gold mine in Mauritania. If the project is approved, it will allow Tasiast to eventually reach a production level of 848,000 oz/y in the five years following the tentative expansion. (Photo courtesy of Kinross Gold)

Kinross Gold announced the results of the feasibility study for a planned expansion project at its Tasiast gold mine in Mauritania. The study, based on an optimal mill size of 38,000 metric tons per day (mt/d), estimates gold production during the first five years of expanded operations (2018 to 2022) at 848,000 oz/y at all-in costs of $792/oz. Cumulative production to 2029 is forecast at 9 million oz.

The Tasiast mine produced 247,818 oz of gold in 2013.

Initial capital expenditure for the expansion is estimated at approximately $1.6 billion, down from a pre-feasibility estimate of $2.7 billion.

Kinross does not expect to make a final construction decision on the Tasiast expansion project until 2015 at the earliest. In the interim, a number of activities will be pursued to maintain project momentum and further enhance the viability of the expansion plan.

The Tasiast feasibility study includes a 3.1-million-oz increase in Tasiast’s estimated mineral reserves to 9.6 million oz. The study is based on replacing the existing 8,000-mt/d mill with a new 38,000-mt/d mill, using heavy fuel oil for power generation at site. The new mill would consist of a primary crusher, a SAG and ball mill grinding circuit, and a conventional carbon-in-leach (CIL) circuit. Overall CIL grades are expected to average 2.09 g/mt for the first five years of expanded production and 1.76 g/mt over the life of the mine.

Existing dump leach facilities would be phased out in 2019 but could be available for lower-grade ore in the future if it becomes economically viable, or if new ore is discovered in near-mine deposits.

Total cash costs of expanded production are estimated to average $501/oz for the first five years of operation and $616/oz life of mine. All-in costs for the first five years of production are forecast at $792/oz, including construction of a sea water pipeline, and $878/oz life of mine.

The Tasiast expansion project is expected to take three years to complete based on a 2015 construction start date and is expected to generate $2.5 billion in free cash flow over the life of the mine.

The expanded project is also expected to generate substantial, positive economic benefits for Mauritania and its people, including a significant increase in GDP resulting from additional taxes, wages, earnings, and locally supplied goods and services.

Resource Center Whitepapers, Videos, Case Studies

Let's stay in touch!

All of the latest mining news and our digital edition sent to your inbox once a week.

We'll never share your email address, and you can opt out at any time, we promise.